ʔapsč iik t̓ašii Multi-use Pathway - Timeline (Summer 2017 - 2022)
Pacific Rim National Park Reserve
2017 - 2018
Summer 2017 |
August: |
Fall 2017 |
Tree felling continued to move south toward Wick Road. November:
|
Winter 2017-18 |
Tree felling concluded and clearing efforts moved on to removal of timber. January: January to March: February: |
Summer 2018 |
Final design changes confirmed and trailbed construction tender package moves into final design stages. Final round of DIA updates began for amendment. |
Fall 2018 |
November: Two First Nation Monitor positions created. |
Winter 2018 |
February: First Nation wood milling contract awarded. |
2019
(subject to change)
Spring 2019 |
DIA amendment to be completed before construction award. EM and construction tenders to be awarded. Two full time First Nation Monitors to be hired. March:
|
Summer 2019 |
Trailbed construction to begin, along with environmental monitoring. Work to be scheduled to avoid periods of highest risk to fisheries, breeding birds and amphibians. Consultations with First Nations on visitor experience and restoration to begin. |
Fall 2019 |
Trailbed construction to continue. |
2020-2022
(subject to change)
2020 | Trailbed construction Installation of clearspan bridges Installation of 63 amphibian pathway crossings and three amphibian highway crossings Widening of highway 4 near the airport |
2021-2022 |
Restoration Plan to be finalized. |
Fall 2020 |
Paving to begin in one coordinated effort for entire pathway. |
2021 | Final touches to be completed on pathway, including pavement markings for pedestrian crossings and trail lanes. |
Winter 2021 - 2022 | Visitor Experience plan and trail amenities to be implemented, including fences, signs, gates, traffic calming features and barricades to be installed along the pathway. |
2022 | ʔapsčiik t̓ašii to open officially in 2022. |
Post-2022 | Active restoration along pathway to occur. |