Transcript
0:08 Hello-Pjila’si-Bonjour Province House National Historic Site is currently
0:14 undergoing its biggest conservation work in it’s 173-year history.
0:20 The Government of Canada is proudly investing in the long-term preservation of Province
0:24 House so it can be enjoyed by future generations.
0:27 Province House belongs to the Province of Prince Edward Island but is maintained and
Project Milestones
0:28 operated as a national historic site by Parks Canada through a 1974 agreement.
0:29 The conservation project is being managed on behalf of Parks Canada by Public Services
0:30 and Procurement Canada, Canada’s centre of expertise for conserving Canada’s built
0:31 heritage.
0:32 In 1843, local architect Isaac Smith began construction on this historic landmark to
0:33 house the provincial legislature, Supreme Court and administrative offices.
0:34 One of the first project milestones to be completed was the stabilization of the porticos.
0:35 The porticos are the “front and back porch” like structures of Province House.
0:38 It is an interesting historical note that in 1844, the design was revised.
0:39 In the original plans, the portico was to be flush with the building- referred to as
0:44 the in antes position.
0:45 However, as you can see, during construction, the decision was made to have the porticos
0:48 project from the building in what conservation architects refer to as the prostyle type.
0:54 From the beginning, the foundations for the porticos were not as deep as the rest of the
0:56 building, as a result of the ad hoc construction phasing, and they began to shift over time.
0:57 The Superintendent of Public Works, Silas Bernard, reported in 1856 that the lack of
0:58 proper foundations at these areas had led to uneven settlement and tenders were called
0:59 for new foundations and steps at the porticos.
1:00 The portico foundations were reconstructed with a loose mixture of stone and rubble,
1:01 using a combination of stone from the Pictou quarries (Nova Scotia) and local PEI sandstones.
1:02 Over the years, water infiltration led to the deterioration of the roof, interior/exterior
1:03 walls and foundation, including the portico foundation.
1:04 Consultants undertook several exploratory investigations to understand the conditions
1:05 of the portico foundations.
1:06 The portico foundation walls were identified as ‘cold’ walls by the project masonry
1:07 consultants.
1:08 Exposed to the environment from all sides, without the benefit of heating from the building,
1:09 the walls were saturated for most of their existence and the freeze-thaw cycling within
Construction
1:10 the walls eroded the interior sandstone and entirely disintegrated the mortar.
1:11 In addition, de-icing salts further eroded the conditions of the mortar and stone.
1:12 The construction for the portico conservation work began in April 2019 and was completed
1:16 in January 2020.
1:19 It took over 15 months to design, plan, and prepare for the construction drawings and
1:24 specifications by a team of dedicated professionals and builders.
1:29 “Parks Canada- Portico”- crew.
1:32 “Today we are marking the completion of the portico foundations, which was a very
1:38 significant part of this project.
1:41 Probably among, if not, the most technically challenging part of this job,” Brian Willis,
1:48 Public Works Canada.
1:50 “Each one of the columns, each one of these four columns had to be suspended, held in
1:55 the air, unmoving, for a period of approximately a week and a half to two weeks,” Brian Willis.
2:01 “So they would apply a load,” Brian Willis.
2:02 “To the jacking frames…They’d hoist them in the air, hoisting is perhaps a strong
2:07 term because they are not really lifting them anywhere, they are moving them less than 1mm,
2:13 and hold them in place, unmoving, get underneath them, pull out all the old foundation stone
2:18 out and then pour a new foundation underneath it, let it back down, move over to the next
2:23 one and do it all over again.
2:24 They did that four times, they did four resets, eight resets, actually there is two porticos,
2:29 they did the north and the south at the same time and they skipped over,” Brian Willis.
2:33 “They started on diagonals and they kept going, and eventually crossed over doing two
2:38 at a time,” Brian Willis.
2:40 Foundation contractor secures reinforcing steel (rebar) for new footings.
2:46 Each new foundation (and jacking structure) were structurally designed to support a load
2:51 of 100 000 lbs.
2:53 That is the equivalent of eight adult elephants!
2:56 South portico column with temporary steel bracing and jacking frame installed.
3:07 This highly sensitive sensor detects any movement in the steel jacking frame (2.01)
3:12 South portico with jacking frame and hydraulic jacking system in place.
3:13 In this frame, the column is actually being “lifted”.
3:14 (2.04) Small excavator used to remove soil from tight
3:15 space between portico columns and main entrance.
3:16 (2.11-2.26) Original stone foundation with section of
3:17 concrete steps removed.
3:18 All of this stone was removed and replaced with a new concrete foundation (2.27)
3:21 Thank you- Wela’lioq-Merci for taking the time to watch this video about the portico
3:27 work.
3:28 Stay tuned for future videos highlighting other elements of the conservation project.
3:34 For more information, or for up-to-date conservation information, visit our website at www.pc.gc/ca/provincehouse